The price shall be paid to the contractor when the work has been completed and has been accepted by the client.
Civil Code
2015 English source edition · Current applicability not established.
This is the 2015 English-language edition attributed in its front matter to the Ministry of Justice. Eri Atlas has not independently verified the translation, later changes, or whether the text is currently in force. Nine passages are incomplete in the available scan and are identified where they occur.
Article 2296
Time for Payment · Preserved transcription; page attribution imported from the source collection. Verify against the original.
The work is completed when it is ready to be used for its intended purpose.
Where partial deliveries and payments have been agreed, the price attaching to each part of the work shall be paid at the time of the delivery and acceptance of that part.